Chinese New Year Factory Closure: A 2027 Planning Guide for UK Importers

November 22, 2026

By Charlotte Henson

Your goods can be ready on time and still miss the boat, if the factory closes for Chinese New Year first. The fix is simple: plan backwards from the closure date, starting now.

Quick answer: China’s official Spring Festival holiday in 2027 runs from Friday 5 February to Saturday 13 February (9 days), with Sundays 31 January and 14 February as working days. Many factories stop earlier and restart later than the official dates, so UK importers should confirm each supplier’s closure and restart dates in writing, place orders early enough to ship before the break, and plan for a slow restart afterwards.

What you’ll learn

  • The official 2027 holiday dates and what the closure means in practice
  • Why orders slip before and after the holiday
  • A week-by-week planning timeline for UK importers
  • How to work out your last safe order date, with a worked example
  • Common mistakes and answers to frequent questions

Contents: What happens | 2027 dates | Why it matters | Planning timeline | Last safe order date | Common mistakes | FAQs | Conclusion

Shipping from China before February? Read about our China sourcing services or contact Avartek Sourcing to talk through your timeline.

What happens to Chinese factories at Chinese New Year?

Chinese New Year, also called the Spring Festival, is China’s biggest holiday. Workers travel home, factories stop production and offices close. For anyone who buys from China, that means a Chinese New Year factory closure that can last longer than the official public holiday.

The official dates are only the legal minimum. A factory may stop loading cargo days before the holiday starts, and some staff return late, so the real gap between your last shipment and your first restarted production run is often wider than nine days. Your supplier is the only reliable source for their own dates.

Chinese New Year 2027 dates

The General Office of the State Council announced the 2027 holiday arrangement on 5 November 2026. You can read the notice on the China government website, which is in Chinese. The Spring Festival lines give these dates:

Item Date
Spring Festival holiday Friday 5 February to Saturday 13 February 2027 (9 days)
Lunar New Year’s Eve Friday 5 February
First day of the new lunar year Saturday 6 February
Working Sunday before the holiday 31 January
Working Sunday after the holiday 14 February

Those two Sundays are make-up working days, so offices and factories that follow the notice will work them. Ask whether your supplier does.

Why it matters for UK importers

Chinese New Year production delays come from the weeks around the holiday, not just the holiday itself.

  • Production slows down before it stops. Staff leave early and factories rush to finish orders, which is when mistakes creep in.
  • Restart is slow. Some workers return late and new staff may need training. First batches after the holiday deserve closer checking.
  • Logistics get tight. Ask your forwarder whether ports and customs offices in your loading area will run at limited capacity, and book space early.
  • Payments and replies stall. Ask your supplier and your bank for the last day payments can be processed, and expect slow replies during the break.
  • Your UK deadlines do not move. Seasonal stock, retail launches and Amazon restocks all need goods on time. Our step-by-step guide to importing from China to the UK shows where time is lost along the way.

A planning timeline for UK importers

Use this as a suggested schedule, counted back from the holiday. Counted back from 5 February 2027, late November leaves about 11 weeks. Adjust the dates to your supplier’s actual closure.

When What to do
Now to early December Ask every supplier for their closure dates, last production day, last loading day and restart date, in writing
Mid December Confirm orders that must ship before the holiday. Approve samples, send final specs and artwork, and agree deposit dates
Early January Book freight and inspection dates. Check Incoterms and who arranges loading, using our guide to shipping from China to the UK
Late January Finish production, inspect and load. Remember 31 January is a working Sunday in China
5 to 13 February Treat as closed. Keep contact to genuine emergencies
From 14 February Confirm the restart date and staffing. Plan a check on the first post-holiday batch

For goods that cannot ship before the holiday, decide early whether to wait for the restart or to ask for a partial shipment. Late decisions are the expensive ones.

How to work out your last safe order date

  • Step 1: Get the factory’s last loading date – Ask the supplier for the last day they can load a container before the holiday. Do not assume it is 4 February.
  • Step 2: Subtract production time – Take the production lead time from your order confirmation, counted from the day the factory has your approved sample, specs and deposit.
  • Step 3: Add inspection and loading time – Allow time for finished goods to be checked and for the container to be booked and loaded. Our guide to quality control in China explains the checks you can schedule.
  • Step 4: Add a buffer – Add a buffer for delays, such as late materials or a failed inspection. A week is a sensible starting point, but use your own judgement.
  • Step 5: Count back and confirm – Subtract the total from the last loading date. That is the date by which your order, deposit and approved sample must be in the factory’s hands.

Worked example (illustrative numbers only). The factory says its last loading day is 29 January. Production takes 30 days and you want a 7 day buffer. The latest date to confirm the order is 29 January minus 37 days, which is 23 December. Missing that date means ordering now to ship after the restart.

Common mistakes to avoid

  • Assuming the official dates are the factory dates. Always get the supplier’s own dates in writing.
  • Placing the order in January. By then, many factories are already full.
  • Forgetting the restart. The first weeks after the holiday are often slower and less predictable.
  • Skipping checks on the pre-holiday rush. Busy lines make errors more likely, so inspect.
  • Leaving payments to the last day. Check the last processing day with your bank and supplier.
  • Not telling your own customers. Share your timeline so they can plan stock.

FAQs

When is Chinese New Year in 2027?

The first day of the lunar new year is Saturday 6 February 2027. The official public holiday runs from Friday 5 February to Saturday 13 February 2027.

How long do Chinese factories close for Chinese New Year?

The official holiday is 9 days, but many factories close for longer in practice. Ask your supplier for their closure dates and their restart date.

Should I order before or after Chinese New Year?

If you need goods before the holiday, work backwards from the factory’s last loading day, as shown above. If you cannot make that date, ordering for production after the restart is usually safer than squeezing into a rushed schedule.

Can I still communicate with my supplier during the holiday?

Expect slow or no replies. Agree one contact for genuine emergencies before the break begins.

Does Chinese New Year affect shipping to the UK?

It can, through port capacity, booking space and the factory’s loading dates. Speak to your forwarder early and get written dates.

Conclusion

A Chinese New Year factory closure is predictable, which means it is plannable. Get your supplier’s dates in writing, work back from their last loading day, and book inspection and freight early.

Need help planning orders around the holiday? Explore our inspection services or contact Avartek Sourcing with your products and target dates.

This article gives general information only. Holiday dates come from the State Council notice and factories may close on different dates, so confirm your own suppliers’ schedules.